Question: Previous Page Next Page Page Question 2 (1 point) Saved Consider the following information of a project: Activity Predecessor B C D E Normal time

Previous Page Next Page Page Question 2 (1 point)
Previous Page Next Page Page Question 2 (1 point) Saved Consider the following information of a project: Activity Predecessor B C D E Normal time Crash time Crash Cost (weeks) (weeks) per week 6 5 100 12 6 90 4 3 110 5 3 230 8 5 160 Calculate the minimum cost of crashing by 1 week. Your Answer: 200 Answer Page 2 of 33