Question: Problem 1. (Critical Path Method.) The following table describes each activity's predecessors in a project: Activity Predecessor Duration (weeks) A 9 B A 2 C

Problem 1. (Critical Path Method.) The following

Problem 1. (Critical Path Method.) The following table describes each activity's predecessors in a project: Activity Predecessor Duration (weeks) A 9 B A 2 C 8 D 8 E B, D 7 F E 4 G 4 H B, D, G 3 J 6 K J 10 M G, K 3 N H, M 6 1. Draw a corresponding AON (Activity-on-Node) project network and label the activities and their duration on the diagram. 9