Question: Problem 1 In the network below, you have 1 6 days to finish the project. Use lags / leads to adjust schedule and manually level

Problem 1
In the network below, you have 16 days to finish the project. Use lags/leads to adjust schedule and manually level your resources so that you may not use more than 5 laborers per day at any time, and the cost found at any given time can not exceed $50,000.
\table[[Activity,Duration,IPA,Laborer,Cost],[A,2,-,2,$10,000