Question: Problem 1 : Indirect cost for a project is $ 2 5 0 0 per day. Given the following information, determine an optimum crashing plan.
Problem : Indirect cost for a project is $ per day. Given the following information, determine an optimum crashing plan.
A What is the critical path?
B What is the total cost for the plan?
PLEASE DO IT USING THE CHART IN THE PICTURE AND EXPLAIN HOW WE KNOW BY HOW MUCH TO DECREASE THE DAYS WHEN CRASHING