Question: Problem 1 . Suppose a work package planned to finish today with a budget of $ 2 0 , 0 0 0 . However, this

Problem 1. Suppose a work package planned to finish today with a budget of $20,000. However,
this work has been actually completed three fourths (3/4) and spent $17,500. Determine PV, EV,
and AC as of today.