Question: Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required

Problem 12-09 (Algorithmic)

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

Activity Activity Time (weeks) Probability
A 3 0.29
4 0.38
5 0.29
6 0.04
B 7 0.22
9 0.53
11 0.25
C 9 0.05
11 0.24
13 0.36
15 0.19
17 0.16
D 10 0.59
12 0.41

  1. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
    Activity Base case Worst case Best case
    A _____weeks _____weeks _____weeks
    B weeks weeks weeks
    C weeks weeks weeks
    D weeks weeks weeks
    Total weeks weeks weeks
  2. Use the random numbers 0.7584, 0.7279, 0.4741 and 0.9526 to simulate the completion time of the project in weeks.
    Activity Random Number Completion Time
    A 0.7584 ____weeks
    B 0.7279 weeks
    C 0.4741 weeks
    D 0.9526 weeks
    Total weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!