Question: Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required
Problem 12-09 (Algorithmic)
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:
| Activity | Activity Time (weeks) | Probability | ||
| A | 3 | 0.29 | ||
| 4 | 0.38 | |||
| 5 | 0.29 | |||
| 6 | 0.04 | |||
| B | 7 | 0.22 | ||
| 9 | 0.53 | |||
| 11 | 0.25 | |||
| C | 9 | 0.05 | ||
| 11 | 0.24 | |||
| 13 | 0.36 | |||
| 15 | 0.19 | |||
| 17 | 0.16 | |||
| D | 10 | 0.59 | ||
| 12 | 0.41 | |||
- Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
Activity Base case Worst case Best case A weeks weeks weeks B weeks weeks weeks C weeks weeks weeks D weeks weeks weeks Total weeks weeks weeks
Note that the answer for base case in part A were wrong. I only need the answer for base case. Thank you!
a. Provide the base-case, worst-case, and best-case calculations f the time to com Activity Base case Worst case Best case weeks weeks 4.08 W ks A 3 weeks weeks 06 11 weeks 7 weeks weeks 13.3 weeks 17 9 C Weeks weeks weeks 1.82 12 10 weeks weeks weeks Total 46 29 37.3