Question: Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required

Problem 12-09 (Algorithmic)

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

Activity Activity Time (weeks) Probability
A 3 0.29
4 0.38
5 0.29
6 0.04
B 7 0.22
9 0.53
11 0.25
C 9 0.05
11 0.24
13 0.36
15 0.19
17 0.16
D 10 0.59
12 0.41

  1. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
    Activity Base case Worst case Best case
    A weeks weeks weeks
    B weeks weeks weeks
    C weeks weeks weeks
    D weeks weeks weeks
    Total weeks weeks weeks
    Problem 12-09 (Algorithmic) A project has four activities (A, B, C, andNote that the answer for base case in part A were wrong. I only need the answer for base case. Thank you!

a. Provide the base-case, worst-case, and best-case calculations f the time to com Activity Base case Worst case Best case weeks weeks 4.08 W ks A 3 weeks weeks 06 11 weeks 7 weeks weeks 13.3 weeks 17 9 C Weeks weeks weeks 1.82 12 10 weeks weeks weeks Total 46 29 37.3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!