Question: Problem 2 17. The time-phased net requirements for the base assembly in a table lamp over the next six weeks are Week 1 Requirements 335

Problem 2 17. The time-phased net requirements

Problem 2 17. The time-phased net requirements for the base assembly in a table lamp over the next six weeks are Week 1 Requirements 335 2. 200 3 140 4 440 5 300 6 200 The setup cost for the construction of the base assembly is $200, and the hold- ing cost is $0.30 per assembly per week. 28. a. Solve Problem 17 assuming the following production capacities: Week Capacity 1 600 2 600 3 600 4 400 5 200 6 200