Question: Problem 2 : ( 2 5 Marks ) Draw the node network, perform the CPM calculations, mark the critical path on the network, and complete

Problem 2: (25 Marks)
Draw the node network, perform the CPM calculations, mark the critical path on the network, and complete the table below. All relationships are FS unless otherwise mentioned and a finish date of 31 days is imposed on the project. TABLE MUST BE FILLED or only 50% of grade will be given.
??S??F=-D,LF=,TF??F=-EFF=(Es)min=F
\table[[Activity,Duration,IPA,Lag,ES,EF,LS,LF,TF,FF],[A,5,-,,0,5,,,,],[B,6,A,,5,11,,,,],[C,3,A,,5,8,,,,],[D,5,C-FF,2,7,12,,,,],[,,B,3,14,19,,,,],[E,9,C,,8,17,,,,],[F,8,B, C,,11,19,,,,],[G,5,F,,19,24,,,,],[,,D-SS,3,10,15,,,,],[H,6,F,G,,24,30,24,30,,],[I,8,F,,19,27,,,,]]
Network Diagram:
Problem 2 : ( 2 5 Marks ) Draw the node network,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!