Question: Problem 2 Critical Path A Critical Path Precedence diagram is shown on the next page. The activity number and duration in days is given for
Problem 2 Critical Path
A Critical Path Precedence diagram is shown on the next page. The activity number and duration in days is given for each activity above and below the box respectively.
Determine the following information:
- The duration of the project. 64 days
- The early start date for activity 3 day 34?
- The late start date for activity 4 --
- The total float in activity 5 --
- The free float for Activity 4 --
Determine the critical path (activities U to W to X to Y to Z)
Activity Number LF LS 3 Activity Activity 3 ES Duration EF 0 1 2 7 5 6 Activity 6 Activity 1 Activity 2 Activity 5 4 0 23 10 8 11 Activity 4 5