Question: Problem 2 Critical Path A Critical Path Precedence diagram is shown on the next page. The activity number and duration in days is given for

Problem 2 Critical Path

A Critical Path Precedence diagram is shown on the next page. The activity number and duration in days is given for each activity above and below the box respectively.

Determine the following information:

  1. The duration of the project. 64 days
  2. The early start date for activity 3 day 34?
  3. The late start date for activity 4 --
  4. The total float in activity 5 --
  5. The free float for Activity 4 --

Determine the critical path (activities U to W to X to Y to Z)Problem 2 Critical Path A Critical Path

Activity Number LF LS 3 Activity Activity 3 ES Duration EF 0 1 2 7 5 6 Activity 6 Activity 1 Activity 2 Activity 5 4 0 23 10 8 11 Activity 4 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!