Question: Problem 2 : Fast - Food - Pasta Consider the operations of a fast - food restaurant serving pre - made pasta dishes to its
Problem : FastFoodPasta
Consider the operations of a fastfood restaurant serving premade pasta dishes to its guests. The operation consists of four steps.
Each customer is first greeted and offered a menu and a tray, which takes seconds per customer. There is one employee at this step.
At the second step, the customer places an order for food, which takes an average of seconds. There are two employees in charge of taking food orders.
At the third step, the customer places an order for drinks, which takes an average of seconds. There is one employee in charge of taking drink orders.
Finally, the fourth step is the cash register where one employee collects the necessary payments from the customer. There is one employee at this last step who takes seconds per guest.
Demand for the restaurant is customers per hour. Employees are paid $ per hour.
Question
What is the process capacity in guests per hour?
points
Correct
Thats correct! The capacity of the process equals the capacity of
the bottleneck, ie Step Therefore, the capacity of the process is guestshr
Question
What is the direct labor content, in seconds?
points
Correct
Labor content secondsguest
Question
What is the average labor utilization? If writing as a decimal, please input up to the sixth place, if entering as percentage or whole number, please include decimal up to the fourth place, ex: or
points
Incorrect
Consider using the following expression:
Labor utilization Labor content mcycle time
Question
A bus with people arrives at the restaurant. Starting with an empty system, how long in minutes does it take for these customers to be served?
points
Incorrect
How long does it take to serve the first customer starting with an empty system? How much time does it take for each additional customer to be served?
Question
Due to a recession, demand goes down to guests per hour. What is the cost of direct labor assuming that the restaurant keeps the same staffing level of five employees?
points
No answer
Incorrect
The answer you gave is not a number.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock