Question: Problem 3 (25 points) A power plant operator is considering an investment in increased efficiency of their plant that costs $1.2 million and lasts for

Problem 3 (25 points) A power plant operator is considering an investment in increased efficiency of their plant that costs $1.2 million and lasts for 10 years, during which time it will save $250,000/ year. The investment has no salvage value. The plant has an MARR of 13%. Is the investment viable