Question: Problem 3 ) ( 3 5 points ) Draw the AON network for the following project and answer the questions that follow. a ) Determine
Problem points
Draw the AON network for the following project and answer the questions that follow.
a Determine and slack for each activity and then determine the total project
completion time and the critical path for the project.
a Crash this project to the maximum days it can be crashed at the least cost. Fill out the table
for each day that the project is crashed.