Question: Problem 3 . Delivering Bad News. Project. We had a program going on in the U . S . , a new product that

Problem 3. Delivering Bad News.
Project. "We had a program going on in the U.S., a new product that we were trying to launch. The project was to interface with the India team and to get a major component actually designed and manufactured in India. Goals were getting a cost reduction for the overall product itself [and] transferring expertise and knowledge to the India team-getting them up to speed on what the whole thing was about."
Team. "The lead was a U.S. manager in [the] U.S. The interviewee was also in the U.S., of Indian background, and felt the India team treated him as an American. [Team members in India included] four from India and one from France."
Challenge. "In the U.S., even though it's bad news, people are more open to saying [something like], 'This part of the program has a lot of risks, and just today I found a few more issues and they are going to delay the program by so many weeks.'[In the United States], I think people are a lot more open to saying that [in India]."
 Problem 3. Delivering Bad News. Project. "We had a program going

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!