Question: Problem #3 Given the following data, construct a material requirements plan which will result in 160 units of Parent #1 (Pl) at the beginning of

Problem #3 Given the following data, construct a

Problem #3 Given the following data, construct a material requirements plan which will result in 160 units of Parent #1 (Pl) at the beginning of week 6, and 220 units at the beginning of week 8: Product Structure Tree P1 A(2) B(2) B C(3) C(4) P2 Inventory Information Item PI P2 A B Currently On-Hand 0 0 70 50 1000 Scheduled Lead Rept) Time 1 1 1 3 2000 (WK 2) 2 Order Qty L4L 140 Fixed Q = 500 Fixed Q = 20 Fixed Q - 2000