Question: Problem 3 : The following bar chart shows the activities required to complete a project in six months. After two months on the job (

Problem 3:
The following bar chart shows the activities required to complete a project in six months. After two months on the job (March 1), the contractor concluded that 50% of Activity C was completed, 50% of Activity D was completed, and Activities A and B were 100% completed. The project has cost the contractor "to date" total of $200000.
Using the Earned Value method, determine the SV, SPI, CV, CPI and EAC. Also, State whether the project is over or under budget AND whether it is ahead of or behind schedule.
\table[[Jan.,Feb.,March,April,May,June],[A $100,000,B $30,000,D $80,000,G $70,000,J $200,000,L $20,000
Problem 3 : The following bar chart shows the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!