Question: Question 1 7 . ( 2 5 points ) Project Control - Earned Value ( EV ) The following bar chart shows the activities to

 Question 17.(25 points) Project Control - Earned Value (EV) The following
Question 17.(25 points)
Project Control - Earned Value (EV)
The following bar chart shows the activities to complete a 6-month project. After 3 months on
the job (July 1), the contractor has completed 20% of Activity F,80% of Activity C, and 40% of
Activity E. Activities A, B, and D are fully completed. These activities have accumulated a cost
of $535.
For this point in time, calculate the following:
a) The budgeted cost of work performed (BCWP)=
b) The budgeted cost of work scheduled (BCWS)=
c) Cost variance (as a percentage)=CV(%)=
d) Is the project over or under budget?
e) Schedule variance (as a percentage)=SV(%)=
f) Is the project ahead or behind schedule?
g) Estimated Cost at Completion =EAC=.
bar chart shows the activities to complete a 6-month project. After 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!