Question: Problem 3 You are managing a construction project with a BAC of $ 1 , 4 0 0 , 0 0 0 . You have
Problem
You are managing a construction project with a BAC of $ You have built of the houses, and you have just finished week on the project, out of the scheduled weeks. Your actual cost has been $ so far. Determine the estimate to complete ETC the proiect, and briefly explain what the result means.