Problem 3 You are managing a construction project with a BAC of $1,400,000. You have built 4 of the 5 houses, and you have just finished week 6 on the project, out of the scheduled 11 weeks. Your actual cost has been $800,000 so far. Determine the estimate to complete (ETC) the project, and briefly explain what the result means