Question: Problem 3.17 Time Activity a m b Immediate predecessor/s A 4 8 10 - B 2 8 24 A C 8 12 16 A D
Problem 3.17
Time
Activity a m b Immediate predecessor/s
A 4 8 10 -
B 2 8 24 A
C 8 12 16 A
D 4 6 10 A
E 1 2 3 B
F 6 8 20 E, C
G 2 3 4 E, C
H 2 2 2 F
I 6 6 6 F
J 4 6 12 D, G, H
K 2 2 3 I, J
- Find the CP
- Find the slack activities and their individual values
- Determine the probability if the project is completed in less than equal to 50
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts