Question: Please show work! Problem 3.17 Time Activity a m b Immediate predecessor/s A 4 8 10 B 2 8 24 8 12 16 A D

Please show work!
Please show work! Problem 3.17 Time Activity a m
Problem 3.17 Time Activity a m b Immediate predecessor/s A 4 8 10 B 2 8 24 8 12 16 A D 4 6 10 A E 1 2 3 B F 6 8 20 E, C G 2 3 4 2 2 2 F I 6 6 6 F J 4 6 12 D, G, H K 2 2 3 I, J Draw the network Find the CP Find the slack activities and their individual values Determine the probability if the project is completed in less than equal to 50 E, C