Question: Problem 4 - 1 0 The following table represents a plan for a project: Use Appendix G . TIMES ( D A Y S )

Problem 4-10
The following table represents a plan for a project: Use Appendix G.
TIMES (DAYS)
JOB NO. PREDECESSOR
JOB(S)amb
1-159
211413
312511
41348
52246
63126
743612
85,6135
98147
107345
119,103510
b. Indicate the critical path.
multiple choice 1
1-2-5-8
1-4-7-10-11
1-3-6-8-9-11
1-2-5-8-9-11
c.
What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to2 decimal places.)
Expected completion time
26.67
days
d.
You can accomplish any one of the following atan additional cost of $1,500.If you will save $1,000 for each day that the earliest completion time is reduced, which of the following actions should be taken, if any?
1. Reduce job 7by two days.
multiple choice 2
Yes
No
2. Reduce job 3by two days.
multiple choice 3
Yes
No
3. Reduce job 5by two days.
multiple choice 4
Yes
No
e.
What is the probability that the project will take more than 28 days to complete? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to2 decimal places and final answer to4 decimal places.)
Probability

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!