Question: Problem 4 - 1 0 The following table represents a plan for a project: Use Appendix G . TIMES ( DAYS ) JOB NO .
Problem
The following table represents a plan for a project: Use Appendix G
TIMES DAYS
JOB NO PREDECESSOR
JOBS a m b
b Indicate the critical path.
multiple choice
c
What is the expected completion time for the project? Do not round intermediate calculations. Round your answer to decimal places.
Expected completion time
days
d
You can accomplish any one of the following at an additional cost of $ If you will save $ for each day that the earliest completion time is reduced, which of the following actions should be taken, if any?
Reduce job by two days.
multiple choice
Yes
No
Reduce job by two days.
multiple choice
Yes
No
Reduce job by two days.
multiple choice
Yes
No
e
What is the probability that the project will take more than days to complete? Use Excel's NORMSDIST function to find the correct probability for your computed Zvalue. Do not round intermediate calculations. Round z value to decimal places and final answer to decimal places.
Probability?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock