Question: Problem 4 : ( 2 0 points ) To develop an aggregate plan for January - June, a production manager has collected the following data

Problem 4: (20 points)
To develop an aggregate plan for January-June, a production manager has collected the following data
Cost: (AED)
Inventory holding 10/unit/month
Regular time ,100/hour
Subcontract ,50/unit
Hiring 500/worker
Firing 700/worker
\table[[Month,Jan,Feb,Mar,Apr,May,June,Total],[Demand,500,400,550,600,500,550,3100]]
Other data
Current workforce 10 workers
Labor hour/unit 4 hours
Working days/month 25 days
Working hours/day 8 hours
Evaluate the following strategies
a- Vary the workforce to meet exactly the demand
\table[[Month,Jan,Feb,Mar,Apr,May,June,Total],[Demand,500,400,550,600,500,550,3100],[# workers,,,,,,,],[Production,,,,,,,],[Hiring,,,,,,,],[Firing,,,,,,,]]
b- Produce at constant rate of 500 units/month. Use subcontract when needed
\table[[Month,Jan,Feb,Mar,Apr,May,June,Total],[Demand,500,400,550,600,500,550,3100],[Production,,,,,,,],[Inventory,,,,,,,],[Subcontract,,,,,,,]]
 Problem 4: (20 points) To develop an aggregate plan for January-June,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!