Question: Problem 4 ( 2 0 % ) : The following table shows the summary activities for a construction project. Assuming that one month is equal

Problem 4(20%): The following table shows the summary activities for a construction project. Assuming that one month is equal to 4 weeks, answer the following questions:
A. Assuming that the project overhead is estimated to be $45,000 and the yearly general overhead for the contractor is estimated to be $1,000,000. If the contractor distributes the yearly general overhead over eight projects, the total direct cost is $20,000,000. Draw the expense curve (S-curve) for the project.E. Using Master format, write the cost code for reinforcement steel activity assuming the following: the building will be constructed in April 2024 and will be the third project for this contractor this year. The location of this building is Birzeit University. The code for this Area is 10
(5%)
Problem 3(20%):
A flooring subcontractor must install ceramic in an existing building. Work items related to the subcontractor and the list of equipment and workforce needed to construct the assigned activity are depicted in Tables 1&2. Table 3 provides the composition of the crews and their standard output per day (8 hours).
\table[[Work item,\table[[Estimated],[quantity]],Unit,\table[[Material unit],[cost]]],[\table[[Filling],[material]],900,M3,$6.25
Problem 4 ( 2 0 % ) : The following table shows

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!