Question: Problem 4 (45 Points): Consider the PERT network, as shown below. The duration estimate for each activity is given in the notation o-m-p, where: o-optimistic,

Problem 4 (45 Points): Consider the PERT network,

Problem 4 (45 Points): Consider the PERT network, as shown below. The duration estimate for each activity is given in the notation o-m-p, where: o-optimistic, m - most likely (mode), p - pessimistic. The estimate times are given in weeks. What is the probability that this project will be completed in 81 weeks? Probabilty Table on the next page