Question: Prohlem 3 ( 5 0 Points ) : Consider the PERT network, as shown below. The duration estimate for each activity is given in the

Prohlem 3(50 Points): Consider the PERT network, as shown below. The duration estimate for each activity is given in the notation 0-m-p, where: 0-optimistic, m-most likely (mode), p -pessimistic. The estimate times are given in weeks. What is the probability that this project will be completed in 81 weeks?
Note: For project daration. calculate the longest path:
,te=t0+4tm+tp6
variance =(tp+t06)2
EF=ES+te
LS=LF+te
TF=LS-ES
 Prohlem 3(50 Points): Consider the PERT network, as shown below. The

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!