Question: Problem 4 - 5 ( Algo ) Your project to obtain charitable donations is now 5 0 days into a planned 6 0 - day

Problem 4-5(Algo)
Your project to obtain charitable donations is now 50 days into a planned 60-day project. The project is divided into 3 activities. The
first activity is designed to solicit individual donations. It is scheduled to run the first 44 days of the project and to bring in $26,300.
Even though we are 50 days into the project, we still see that we have only 88% of this activity complete. The second activity relates to
company donations and is scheduled to run for 50 days starting on day 6 and extending through day 56. We estimate that, even
though we should have (4450)88.00% of this activity complete, it is actually only 55% complete. This part of the project was
scheduled to bring in $151,300 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of
the project and has not started. It is scheduled to bring in an additional $52,600. So far, $175,600 has actually been brought in on the
project.
Calculate the Schedule Variance, Schedule Performance Index, and Cost (actually value in this case) Performance Index. (Hint: Note
that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.)
Note: Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values.
Round your "performance index" values to 3 decimal places.
 Problem 4-5(Algo) Your project to obtain charitable donations is now 50

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!