Question: Problem 4 The following table represents a plan for a project: JOB NO. PREDECESSOR JOB(S) d NI B D E F G H 1 J

Problem 4 The following table represents a plan
Problem 4 The following table represents a plan for a project: JOB NO. PREDECESSOR JOB(S) d NI B D E F G H 1 J K $ 3 6 4 1 2 6 4 3 4 6 6 4 7 5 4 3 9 6 7 5 8 7 $ 14 12 7 4 15 8 17 6 10 D E.F G a Construct the appropriate network diagram. b. Indicate the critical path. c. What is the expected completion time for the project? d. What is the probability the project will: take more than 43 days to complote: take less than 42 days to complete, and take between 37 and 42 days to complete