Question: Problem 4-12 (Static) The following table represents a plan for a project: TIMES (DAYS) JOB NO. PREDECESSOR JOB(S) a m b 1 2 3 4

Problem 4-12 (Static)

The following table represents a plan for a project:

TIMES (DAYS)
JOB NO. PREDECESSOR JOB(S) a m b
1 2 3 4
2 1 1 2 3
3 1 4 5 12
4 1 3 4 11
5 2 1 3 5
6 3 1 2 3
7 4 1 8 9
8 5, 6 2 4 6
9 8 2 4 12
10 7 3 4 5
11 9, 10 5 7 8

b. Indicate the critical path.

  • 1-3-6-8-9-11

  • 1-2-5-8-9-11

  • 1-4-7-10-11

c. What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.)

Expected completion time ___ days

d. You can accomplish any one of the following at an additional cost of $1,500. If you will save $1,000 for each day that the earliest completion time is reduced, which of the following actions should be taken, if any?

1. Reduce job 5 by two days.

  • Yes

  • No

2. Reduce job 3 by two days.

  • Yes

  • No

3. Reduce job 7 by two days.

  • Yes

  • No

e. What is the probability that the project will take more than 30 days to complete? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Other than the expected completion time you entered in part c above, do not round intermediate calculations. Round "z" value to 2 decimal places your final answer to 4 decimal places.)

Probability ____

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!