Question: Problem 5-12 (Static) The following table represents a plan for a project: TIMES (DAYS) JOB NO. PREDECESSOR JOB(S) a m b 1 2 3 4
Problem 5-12 (Static)
The following table represents a plan for a project:
| TIMES (DAYS) | ||||||
| JOB NO. | PREDECESSOR JOB(S) | a | m | b | ||
| 1 | 2 | 3 | 4 | |||
| 2 | 1 | 1 | 2 | 3 | ||
| 3 | 1 | 4 | 5 | 12 | ||
| 4 | 1 | 3 | 4 | 11 | ||
| 5 | 2 | 1 | 3 | 5 | ||
| 6 | 3 | 1 | 2 | 3 | ||
| 7 | 4 | 1 | 8 | 9 | ||
| 8 | 5, 6 | 2 | 4 | 6 | ||
| 9 | 8 | 2 | 4 | 12 | ||
| 10 | 7 | 3 | 4 | 5 | ||
| 11 | 9, 10 | 5 | 7 | 8 | ||
b. Indicate the critical path.
- A) 1-2-5-8-9-11
- B) 1-3-6-8-9-11
- C) 1-4-7-10-11
c. What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.)
Expected completion time ________.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts