Question: Problem 4-14 (Static) Here is a CPM network with activity times in weeks: (B(5) (C(6) (A(7) G(3) D(6) E(4) F(8) a. Determine the critical path.

Problem 4-14 (Static) Here is a CPM network withProblem 4-14 (Static) Here is a CPM network with

Problem 4-14 (Static) Here is a CPM network with activity times in weeks: (B(5) (C(6) (A(7) G(3) D(6) E(4) F(8) a. Determine the critical path. O A-B-C-D A-E-F-D O A-E-G-C-D b. How many weeks will the project take to complete? Number of weeks c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration? Number of weeks reduced