Question: Problem 4-15 For the network shown: a-1. Determine the critical path. multiple choice 1 A-B-D-G A-C-F-G A-B-E-G Incorrect A-C-E-G a-2. Determine the early completion time
Problem 4-15
| For the network shown:
|
| a-1. | Determine the critical path. |
multiple choice 1
|
| a-2. | Determine the early completion time in weeks for the project. |
| Early completion time | 25 Numeric ResponseEdit Unavailable.25incorrect.weeks |
| For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened. |
| ACTIVITY | NORMAL TIME | NORMAL COST | CRASH TIME | CRASH COST | ||||
| A | 4 | $ | 7,100 | 3 | $ | 13,500 | ||
| B | 10 | 12,500 | 3 | 19,500 | ||||
| C | 4 | 5,600 | 2 | 7,200 | ||||
| D | 6 | 4,200 | 4 | 5,600 | ||||
| E | 7 | 3,400 | 3 | 6,400 | ||||
| F | 7 | 6,300 | 2 | 7,800 | ||||
| G | 4 | 7,200 | 1 | 9,600 | ||||
| b-1. | Which activities in order of reduction would be shortened? |
multiple choice 2
|
| b-2. | Find the resulting cost to crash. |
| Resulting cost | $ |