Question: Problem 5-17 For the network shown: a-1. Determine the critical path. A) A-B-D-G B) A-C-E-G C) A-B-E-G D) A-C-F-G a-2. Determine the early completion time
Problem 5-17
For the network shown:

a-1. Determine the critical path.
- A) A-B-D-G
- B) A-C-E-G
- C) A-B-E-G
- D) A-C-F-G
a-2. Determine the early completion time in weeks for the project.
Early completion time _____ weeks
For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.
| ACTIVITY | NORMAL TIME | NORMAL COST | CRASH TIME | CRASH COST | ||||
| A | 7 | $ | 7,900 | 4 | $ | 13,000 | ||
| B | 8 | 12,800 | 6 | 18,900 | ||||
| C | 7 | 5,200 | 5 | 7,200 | ||||
| D | 9 | 4,700 | 8 | 5,700 | ||||
| E | 5 | 3,800 | 4 | 6,100 | ||||
| F | 4 | 6,400 | 3 | 8,600 | ||||
| G | 4 | 7,900 | 3 | 8,000 | ||||
b-1. Which activities in order of reduction would be shortened?
- A) G-E-A
- B) B-G-D
- C) G-D-A
- D) D-B-C
b-2. Find the resulting cost to crash.
Resulting cost $ _______
DI9) (B(8) A (7) (E(5) G4) ) C) F(4)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts