Question: Problem 5-17 For the network shown: a-1. Determine the critical path. A) A-B-D-G B) A-C-E-G C) A-B-E-G D) A-C-F-G a-2. Determine the early completion time

Problem 5-17

For the network shown:

Problem 5-17 For the network shown: a-1.

a-1. Determine the critical path.

  • A) A-B-D-G
  • B) A-C-E-G
  • C) A-B-E-G
  • D) A-C-F-G

a-2. Determine the early completion time in weeks for the project.

Early completion time _____ weeks

For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.

ACTIVITY NORMAL TIME NORMAL COST CRASH TIME CRASH COST
A 7 $ 7,900 4 $ 13,000
B 8 12,800 6 18,900
C 7 5,200 5 7,200
D 9 4,700 8 5,700
E 5 3,800 4 6,100
F 4 6,400 3 8,600
G 4 7,900 3 8,000

b-1. Which activities in order of reduction would be shortened?

  • A) G-E-A
  • B) B-G-D
  • C) G-D-A
  • D) D-B-C

b-2. Find the resulting cost to crash.

Resulting cost $ _______

DI9) (B(8) A (7) (E(5) G4) ) C) F(4)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!