Question: Problem 5 - 1 1 ( Algo ) There is an 8 4 percent chance the project below can be completed in X weeks or

Problem 5-11(Algo)
There is an 84 percent chance the project below can be completed in X weeks or less.
A diagram shows circles labeled A, B, C, D and E. A connects to B and C. B leads to D and C to E.
ACTIVITY MOST OPTIMISTIC MOST LIKELY MOST PESSIMISTIC
A 4314
B 555
C 3510
D 5811
E 41010
What is X?
Note: Do not round intermediate calculations. Round your answer to the nearest whole number.