Question: Problem 5: (5 marks) A work center has the following open and planned orders for a given week. Calculate the total standard time required
Problem 5: (5 marks) A work center has the following open and planned orders for a given week. Calculate the total standard time required (load) (5 marks): Order Qty Setup Time Run Time Total (hours) Time (hours) (hours) Released Orders Part # A111 380 1.50 0.10 Part # 8222 240 3.00 0.30 Planned Orders Part # C333 360 2.50 0.25 Part # D444 440 2.00 0.15 Total Time (standard hours)