Question: Problem 5 - 8 ( Algo ) Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR, table [ [

Problem 5-8(Algo)
Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,\table[[TIME],[(WEEKS)]]],[A,-,2],[B,A,3],[C,A,5],[D,B,4],[E,C8media:cm.png%,7],[F,D,2],[G,D,3],[H,F,7]]
b. What is the critical path?
A-B-D-F-G-H
A-B-D-E-H
A-C-E-F-G-H
A-C-E-H
c. How many weeks will it take to complete the project?
Number of weeks
 Problem 5-8(Algo) Schedule the following activities using CPM: \table[[ACTIVITY,IMMEDIATE PREDECESSOR,\table[[TIME],[(WEEKS)]]],[A,-,2],[B,A,3],[C,A,5],[D,B,4],[E,C8media:cm.png%,7],[F,D,2],[G,D,3],[H,F,7]] b.