Question: Problem 5-14 Here is a CPM network with activity times in weeks: A(7) B(7) C(6) G(5) D(6) E(5) F(8) a. Determine the critical path. A-E-G-C-D
Problem 5-14
Here is a CPM network with activity times in weeks:
A(7) B(7) C(6)
G(5) D(6)
E(5) F(8)
a. Determine the critical path.
| A-E-G-C-D | |
| A-B-C-D | |
| A-E-F-C-D | |
| A-E-F-D |
b. How many weeks will the project take to complete?
Number of weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts