Question: Problem 5-14 (Static) Here is a CPM network with activity times in weeks: A(7) B(5) E(4) a. Determine the critical path. OA-E-G-C-D O A-B-C-D OA-E-F-D
Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-G-C-D A-B.C-D A-E-F-D b. How many weeks will the project take to complete
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts