Question: Problem 5-14 (Static) Here is a CPM network with activity times in weeks: A(7) B(5) E(4) a. Determine the critical path. OA-E-G-C-D O A-B-C-D OA-E-F-D

Problem 5-14 (Static) Here is a CPM network with activity times in weeks: A(7) B(5) E(4) a. Determine the critical path. OA-E-G-C-D O A-B-C-D OA-E-F-D Number of weeks (G(3) b. How many weeks will the project take to complete? (C(6) (F(8) (D(6)
 Problem 5-14 (Static) Here is a CPM network with activity times

Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-G-C-D A-B.C-D A-E-F-D b. How many weeks will the project take to complete