Question: Problem 7 : A project to develop technology training seminars is 5 days behind schedule at day 6 5 . It had a planned cost
Problem : A project to develop technology training seminars is days behind schedule at day It had a planned cost of $ for this point in time, but the actual cost is only $ Estimate the schedule and cost variances.