Question: A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point
Step by Step Solution
3.46 Rating (166 Votes )
There are 3 Steps involved in it
000 AC 550 AC 750 Day AC PV EV Day AC PV EV 65 550 73... View full answer