Question: Problem 8: A task has an optimistic completion time of 6 days, a most likely completion time of 9 days, and a pessimistic completion
Problem 8: A task has an optimistic completion time of 6 days, a most likely completion time of 9 days, and a pessimistic completion time of 12 days. a) What is the expected completion time? b) What is the variance of the task's completion time?
Step by Step Solution
3.42 Rating (152 Votes )
There are 3 Steps involved in it
To find the expected completion time and the variance ... View full answer