Question: Problem 9 - 0 9 ( Algorithmic ) requisite activities and related information in the following table ( duration estimates measured in days ) .

Problem 9-09(Algorithmic) requisite activities and related information in the following table (duration estimates measured in days).
\table[[\table[[Activity]],\table[[Immediate],[Predecessor(s)]],Most],[Optimistic,Probable,Pessimistic],[\table[[A: Negotiate contract with],[selected musicians]],-,10,11,12],[B: Reserve site,-,8,10,12],[\table[[C: Manage travel logistics],[for music group]],A,2,7,9],[\table[[D: Screen & hire],[security personnel]],B,4,5,j],[\table[[E: Arrange advertising],[& ticketing]],C,7,7,7],[F: Hire parking staff,A,D,8,9,16],[G: Arrange concession sales,E,6,7,11]]
a. Which project network is correct?
(i)
(ii)
(iii)
(iv)
b. Compute the expected duration and variance of each activity. If required, round your answer to two decimals. If your answer is zero, enter "0".
\table[[Activity,Expected Time,Variance],[A,,],[B,,],[C,,],[D,,],[E,,],[F,,],[G,,]]
Critical
\table[[Activity,ES,LS,EF,LF,Slack,Activity],[A,,,,,,],[B,,,,,,v],[C,,,,,,:'
 Problem 9-09(Algorithmic) requisite activities and related information in the following table

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!