Question: At a local university, the Student Commission on Programming and Entertainment ( SCOPE ) is preparing to host its first rock concert of the school
At a local university, the Student Commission on Programming and Entertainment SCOPE is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table duration estimates measured in days
tableActivitytableImmediatePredecessorstableOptimistictableMostProbablePessimisticA: Negotiate contract with,tableselected musicianstableB: Reserve siteC: Manage travel logisticsfor music groupAD: Screen & hire,,,, security personnel,BE: Arrange advertising,B C & ticketing,,,F: Hire parking staff,D
a Draw the project network.
b Compute the expected duration and variance of each activity.
c Determine the critical path in the project network.
d What is the expected duration and variance of the critical path?
e Based only on the critical path, what is the likelihood that the project will be completed within days?
f If activity B is delayed by six days beyond its early start time, how does this affect the expected project duration?
g Using all paths through the project network, estimate the probability that the project will be completed within days. Compare your answer to the answer in part e and explain.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock