Question: Problem Statement: A client has awarded you a project to design an automated assembly system for crayon manufacturing. Requirements include: Production rate = 1 4
Problem Statement:
A client has awarded you a project to design an automated assembly system for crayon manufacturing.
Requirements include:
Production rate million crayonsday
Project budget $ million
Project delivery months
Manufacturing Process:
The steps for manufacturing are:
Melt the wax.
Mix pigment with wax.
Inject uniformly mixed wax into mould.
Cool the mixture in the mould.
Inspect for crayon defects such as air bubbles.
Double wrap the crayons
Sort the crayons by colour.
Package different colours of crayons into one box.
Package the boxes and ship the crayons.
Figure Quality Function Deployment.
Figure Quality Function Deployment Example.
Objectives:
The main objectives of this assessment are to:
understand and explain the process flow
identify automation potential
describe and justify the instrumentation required for automation
prepare process and instrumentation documentation
Assessment Tasks:
Task : Identify System Requirements marks
You may use Quality Function Deployment QFD or other methods to list out the requirements. You may make some assumptions about some items in QFD
Note: Often the customer will provide a product part list, available budget, desired production rate, delivery time, system uptime, and space constraints. For a system integrator, the focus is to understand the requirements from the customers in as much detail as possible. Common requirements include cost, production rate, system up time, and delivery time. Problem statement provides some customer requirements from the crayon manufacturing case study. Your proposed
conceptual design in the proposal should transform these needs into concrete design features that achieve the requirements.
Task : Collect Data marks
Provide a list or table of data collected in relation to the design.
Note: An application engineer at a system integration company will want to collect as much detail as possible about the part list, process requirements, and how parts will be presented to the assembly line. For example, will the parts be delivered in a tray or a box? Will they come from another sub assembly line or be shipped from a vendor? Is a machine needed to check the parts before assembly? How big is a lot? How often do you need to refill the part feeder? Are there any preexisting machines that need to be incorporated into the line?
Task : Determine the Assembly Sequence and Cycle time marks
Given the required production rate, system uptime and part list, an optimum assembly manufacturing sequence needs to be designed. Draw a precedence diagram example shown in Figure that should be constructed based on operations precedence relationships; then a line balancing method, such as Largestcandidate rule, should be employed to combine work elements into a workstation, and the original cycle time needs to be calculated. After that, balance delay can be calculated to measure line inefficiency and the original cycle time should be compared with the desired cycle time derived from the predicted production rate.
Parallel workstations andor multiple identical production lines will be arranged to reduce default cycle time andor reach the desired production rate. Figure shows example of parallel workstation and parallel lines arrangements, and Figure shows the example calculation of cycle time.
The desired workstation arrangement is for each station to have the same operation time and the line inefficiency to be zero.
Figure Example precedence diagram.
Figure Example cycle time calculation.
Task : Select Assembly Line Components marks
This task involves making decisions about the number of machines for each station; the types of machines and machine capacity for each station; types of material handling and transfer equipment needed, types of part feeders and machine tools required, number of operators, and number of work shifts needed to manage the assembly lines. All these factors will affect the overall cost of the proposed design. Therefore, a few alternatives may be proposed. For example, in this crayon manufacturing system, to achieve the desired production rate of million units per day, the design can incorporate parallel stationsmachines
Task : Determine Layout of Assembly Line marks
There are three common line layouts: inline, Ushape and parallel cell configurations. The goal is to reduce material transfer time since transfer is not a valueadded process and to increase the feedback. Present the layout suitable for the requirements of the design.
Task : Perform Cost Estimation and Analysis marks
Cost categories include labour cost, machineequipment cost materials cost, system development cost, and overhead. Several alternatives may be proposed. Cu
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
