Question: Problem statement for Questions 6 to 1 0 : Perform earned value analysis using the details presented below and calculate BCWS , BCWP , ACWP,
Problem statement for Questions to : Perform earned value analysis using the details presented below and calculate BCWS BCWP ACWP, Schedule Performance Index and Cost Performance Index.
The project status at the end of working days is presented below:
i Activity A : done, used workersday at the cost of Rs day
ii Activity B: done, used workersday at the cost of Rs day
iii Activity C : done, used workers day at the cost of Rs per day
iv Activity D: not yet started;
point
Which of the following is true?
The project is ahead of schedule and under the budget.
The project is behind the schedule and under the budget.
The project is ahead of schedule and over the budget.
The project is behind the schedule and over the budget.
point
BCWS at the project level as on status date:
point
BCWP at the project level as on status date:
point
ACWP at the project level as on status date:
point
SPI and CPI values are
SPI is and CPI is
SPI is and CPI is
SPI is and CPI is
SPI is and CPI is
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock