Question: Problem statement for Questions 6 to 1 0 : Perform earned value analysis using the details presented below and calculate BCWS , BCWP , ACWP,

Problem statement for Questions 6 to 10: Perform earned value analysis using the details presented below and calculate BCWS, BCWP, ACWP, Schedule Performance Index and Cost Performance Index.
The project status at the end of 5 working days is presented below:
i) Activity A : 100% done, used 3 workers/day at the cost of Rs.650/ day
ii) Activity B: 30% done, used 7 workers/day at the cost of Rs.650/ day
iii) Activity C : 80% done, used 6 workers /day at the cost of Rs.650 per day
iv) Activity D: not yet started;
1 point
Which of the following is true?
The project is ahead of schedule and under the budget.
The project is behind the schedule and under the budget.
The project is ahead of schedule and over the budget.
The project is behind the schedule and over the budget.
1 point
BCWS at the project level as on status date:
18200
18400
18600
18800
1 point
BCWP at the project level as on status date:
12640
12660
12680
12700
1 point
ACWP at the project level as on status date:
29000
29250
29500
29750
1 point
SPI and CPI values are
SPI is 0.7 and CPI is 0.4
SPI is 0.9 and CPI is 0.6
SPI is 1.1 and CPI is 0.8
SPI is 1.3 and CPI is 1.0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!