Question: (Process Analysis with One Flow Unit) Consider a process consisting of three resources: What is the bottleneck? What is the process capacity? What is the
(Process Analysis with One Flow Unit) Consider a process consisting of three resources:
![Resource 1 2 23 Activity Time [Min./Unit] 10 6 3 16 Number](https://dsd5zvtm8ll6.cloudfront.net/images/question_images/1735/0/2/2/998676a5996266401735022996706.jpg)
What is the bottleneck? What is the process capacity? What is the flow rate if demand is eight units per hour? What is the utilization of each resource if demand is eight units per hour?
Resource 1 2 23 Activity Time [Min./Unit] 10 6 3 16 Number of Workers 2 3 13
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts