Question: Process Flow - Service or Product 1 . How many units cannthe system process during an eight - hour shift? 2 . What is the

Process Flow
-
Service or Product
1
.
How many units cannthe system process during an eight
-
hour shift?
2
.
What is the cycle time of the system?
3
.
At what rate should raw material be released to Operation A
?
Why?
4
.
What minimal actions could you take to double capacity?
(
Assume
that it is possible to obtain funds for extra equipment or to hire extra
labour
)
5
.
Which operation is the bottleneck of the overall system? How do you
know?