Question: Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule. Job A
Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule.
| Job | A | B | C | D | E |
| Processing time (weeks) | 2 | 0.5 | 1 | 3 | 1.5 |
| Due time (weeks) | 3 | 6 | 4 | 5 | 2 |
a. What would be the lateness of Job B?
b. What would be the tardiness of Job E?
c. what is the maximum tardiness for this set of jobs?
d. what is the average flow time for this set of jobs?