Question: Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule. Job A
Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule.
| Job | A | B | C | D | E |
| Processing time (weeks) | 2 | 1.5 | 1 | 4 | 0.5 |
| Due time (weeks) | 3 | 7 | 2 | 1 | 4 |
what would be the lateness of job B
what would be the tardiness of job E
what is the maximum tardiness for this set of jobs
what is the average flow time for this set of jobs